Skip to main content
NTMWD Logo
File #: 25-6203    Version: 1
Type: Administrative Memorandum Status: Agenda Ready
File created: 10/9/2025 In control: Board of Directors
On agenda: 10/23/2025 Final action:
Title: Stover Creek Force Main; Project No. 501-0624-23; Resolution No. 25- 52; Right of Way Acquisition Program
Indexes: .UEFIS - Upper East Fork Interceptor System
Code sections: 501-0624-23 - Stover Ck Force Main
Attachments: 1. Resolution, 2. Map
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
Upper East Fork Interceptor System

title
Stover Creek Force Main; Project No. 501-0624-23; Resolution No. 25- 52; Right of Way Acquisition Program
end


SUBJECT

recommendation
Adopt Resolution No. 25-52 authorizing an amendment to an existing right of way acquisition program to provide additional funding in the amount of $24,700,000.
end


PURPOSE

Right of way acquisition for this project is being performed in phases. Phase 1 was partially funded in April 2024. The additional funding being requested is for the remainder of Phase 1 as well as Phases 2, 3, and 4.


RECOMMENDATION

The Executive Director and NTMWD staff recommend the Board of Directors:

1) Authorize the Executive Director to amend a previously executed right-of-way acquisition program for the Stover Creek Force Main, Project No. 501-0624-23, by providing additional funding of $24,700,000, resulting in a total budget of $32,700,000; and,

2) Adopt Resolution No. 24-52, "A Resolution Authorizing the Use of Eminent Domain to Acquire Right-of-Way for the Stover Creek Force Main, Project No. 501-0624-23, and Delegating Authority to Initiate Condemnation Proceedings to the NTMWD Executive Director."

Consultant:

N/A


Scope:

Right-of-Way acquisition and the necessary support services to facilitate the purchasing of easements for the project.


Project:

501-0624-23, Stover Creek Force Main


Amount:

$24,700,000 additional funding


Committee:
This will be an item on the October 22, 2025, Real Estate Committee Agenda




DRIVER(S) FOR THIS PROJECT

Strategic Objective:
1.2 - Successfully Deliver Capital Program


? Regulatory Compliance
? Asset Condition
? Capacity
? Redundancy/Resiliency
? Relocation or External Requests
? Operational Efficiency
? Safety
? Administrative
? Policy
? Other _____________


BACKGROUND

PROJECT PURPOSE
* Ad Memo 24-6017, April 2024, authorized funding in the amount of $2,331,606 for the right-of-way (ROW) support services to Lockwood, Andrews, and Newman, Inc. (LA...

Click here for full text