Legislation Details

File #: 26C-38    Version: 1
Type: Consent Agenda Item Status: Agenda Ready
File created: 8/11/2026 In control: Board of Directors
On agenda: 8/27/2026 Final action:
Title: Leonard Water Treatment Plant Phase III; Project No. 101-0653-24; Resolution No. 26-36; Request for Authorization to allow use of Alternate Project Delivery Method
Indexes: .RWS - Regional Water System, Authorization to use CMAR Delivery Method
Code sections: 101-0653-24 - Leonard WTP Phase III
Attachments: 1. Resolution, 2. Map
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
Regional Water System

title
Leonard Water Treatment Plant Phase III; Project No. 101-0653-24; Resolution No. 26-36; Request for Authorization to allow use of Alternate Project Delivery Method

end
SUBJECT

recommendation
Adopt Resolution No. 26-36 authorizing the use of Construction Manager At-Risk (CMAR) project delivery method for the Leonard Water Treatment Plant Phase III expansion project.

end
PURPOSE

The use of the CMAR delivery method will provide best value to NTMWD given the multi-phased construction approach for Leonard Water Treatment Plant (WTP) Phase III expansion. CMAR project delivery provides a distinct advantage of early identification and procurement of major construction materials and equipment that have traditional long lead times for configuration approvals, fabrication, and delivery to the project site. Items with long lead time specific to this project include process equipment, large diameter pipes and valves. This delivery approach allows the procurement process to progress concurrently with the detailed design, which helps compress the project's schedule. Using CMAR for the Leonard WTP Phase III expansion will promote cost certainty and cost transparency for NTMWD while leveraging CMAR inputs during the design phase to identify and manage project risks.

RECOMMENDATION

The Executive Director and NTMWD staff recommend the Board of Directors adopt Resolution No. 26-36, "A Resolution authorizing the use of this alternative delivery approach in accordance with Texas Government Code Chapter 2269, Contracting and Delivery Procedures for Construction Projects."


Contractor:
N/A


Scope:
CMAR Project Delivery Method


Project:

No. 101-0653-24, Leonard Water Treatment Plant Phase III


Amount:
N/A


Committee:
This will be a Champion Update at the August 26, 2026 Real Estate committee meeting


DRIVER(S) FOR THIS PROJECT

Strategic Objective:
1.2 Successfully Deliver Capital Program
...

Click here for full text