File #: 24C-44    Version: 1
Type: Consent Agenda Item Status: Agenda Ready
File created: 11/5/2024 In control: Board of Directors
On agenda: 11/21/2024 Final action:
Title: ??Texoma Raw Water Pipeline No. 2 and Texoma Raw Water Pipeline to Leonard Water Treatment Plant (WTP) Pipeline - Request for Authorization to allow use of Alternate Project Delivery Method; Project No. 101-0633-23 and No. 101-0642-24; Resolution No. 24-48?
Sponsors: Water Committee - Committee Action
Indexes: .RWS, Authorization to use CMAR Delivery Method
Code sections: 101-0633-23 - Texoma Raw Water Pipeline No 2 , 101-0642-24 - Texoma Raw Water Pipeline to Leonard WTP Pipeline
Attachments: 1. Resolution, 2. Map
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
???Regional Water System???

title
??Texoma Raw Water Pipeline No. 2 and Texoma Raw Water Pipeline to Leonard Water Treatment Plant (WTP) Pipeline - Request for Authorization to allow use of Alternate Project Delivery Method; Project No. 101-0633-23 and No. 101-0642-24; Resolution No. 24-48?
end

SUBJECT

recommendation
??Authorize the use of Construction Manager at-Risk (CMAR) project delivery method for the Texoma Raw Water Pipeline No. 2 and the Texoma Raw Water Pipeline to Leonard Water Treatment Plant (WTP) Pipeline project.??
end

PURPOSE

?The use of CMAR project delivery method will provide the best value to NTMWD and in this case the opportunity to combine these two similar capital projects to leverage the advantages of early procurement of certain long lead time materials and equipment. This allows the procurement process to progress concurrently with the detailed design, helping to compress project schedule.

RECOMMENDATION

??The Executive Director and NTMWD staff recommend the Board of Directors adopt Resolution No. 24-48, A Resolution authorizing the use of this alternative delivery approach in accordance with Texas Government Code Chapter 2269, Contracting and Delivery Procedures for Construction Projects.??


Project:

No. 101-0633-23, Texoma Raw Water Pipeline No. 2 and No. 101-0642-24, and Texoma Raw Water Pipeline to Leonard WTP Pipeline


Committee:
This will be an item on the November 20, 2024, Water Committee meeting agenda










DRIVER(S) FOR THIS PROJECT

Strategic Objective:
1.1 High Quality Services
1.4 Reliable and Resilient System Capacity

? Regulatory Compliance
? Asset Condition
? Capacity
? Redundancy/Resiliency
? Relocation or External Requests
? Operational Efficiency
? Safety
? Administrative
? Policy
? Other _____________

BACKGROUND

??The Texoma Raw Water Pipeline No. 2 increases the capacity of raw water transfer fr...