File #: 25C-36    Version: 1
Type: Consent Agenda Item Status: Agenda Ready
File created: 6/13/2025 In control: Board of Directors
On agenda: 6/26/2025 Final action:
Title: Interlocal Cooperation Agreement between the North Texas Municipal Water District and East Fork Special Utility District for Water Line Installation at Muddy Creek Wastewater Treatment Plant
Indexes: .RWS - Regional Water System
Attachments: 1. Resolution, 2. Map, 3. Exhibit A, 4. Interlocal Agreement
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
Region Wastewater System

title
Interlocal Cooperation Agreement between the North Texas Municipal Water District and East Fork Special Utility District for Water Line Installation at Muddy Creek Wastewater Treatment Plant
end


SUBJECT

recommendation
Authorize Resolution 25-33 for the execution of an Interlocal Cooperation Agreement between the North Texas Municipal Water District and East Fork Special Utility District for the installation of a water line at Muddy Creek Wastewater Treatment Plant.
end


PURPOSE

East Fork Special Utility District (EFSUD) plans to extend its potable water system and wishes to locate a portion of a pipeline across the Muddy Creek Wastewater Treatment Plant (WWTP) property. EFSUD would provide retail portable water services to Muddy Creek WWTP and certain retail water customers currently serviced by NTMWD.


RECOMMENDATION

The Executive Director and NTMWD staff recommend the Board of Directors authorize the Executive Director to execute an ILA as follows:

1) Authorize the Executive Director to execute an Interlocal Cooperation Agreement with the East Fork Special Utility District.

2) Adopt Resolution 25-33 "A Resolution Authorizing an Interlocal Cooperation Agreement Between North Texas Municipal Water District and the East Fork Special Utility District for Water Line Installation at Muddy Creek Wastewater Treatment Plant".

Contracting Party:
East Fork Special Utility District (East Fork SUD)


Purpose:
Execution of Interlocal Cooperation Agreement


Project:

East Fork Special Utility District for Water Line Installation at Muddy Creek Wastewater Treatment Plant


Amount:
N/A


Committee:
This item was an Engineering and Planning Update on the June 11, 2025, Executive Committee meeting, and will be a Champion Update at the June 25, 2025, Wastewater Committee meeting


DRIVER(S) FOR THIS PROJECT

Strategic Objective:
3.3 Durable Strategic Partnerships


? Regulatory Compliance
? Asset Condition
? Capacity
? Redundancy/Re...