Upper East Fork Interceptor System
title
Stover Creek Force Main Segment B, Project No. 501-0624-23; Tabulation of Bids, Award of Contract for Segment B, Engineering Services Agreement, and Authorize Inspection Services
end
SUBJECT
recommendation
Authorize award of a construction contract for Segment B in the amount of $12,939,441 to McKee Utility Contractors, LLC, authorize funding in the amount of $1,131,457 for an engineering services agreement with Lockwood Andrews & Newnam, Inc. for engineering services during construction, and authorize funding in the amount of $1,606,176 for internal inspection services for the Stover Creek Force Main project.
end
PURPOSE
The purpose of this project is to increase wastewater conveyance capacity of the Upper East Fork Interceptor System (UEFIS) by constructing a new lift station and force main to serve projected growth in McKinney and Prosper north of US Highway 380 (US 380), return capacity to the McKinney-owned sewers, and reduce the risk of sanitary sewer overflows in the UEFIS. All flows entering the Stover Creek Lift Station and Force Main are to be conveyed and treated at the Sister Grove Regional Water Resource Recovery Facility (RWRRF) via either direct conveyance or, on an interim basis, through existing NTMWD-owned conveyance systems.
RECOMMENDATION
The Executive Director and NTMWD staff recommend the Board of Directors authorize the award of a contract and services as follows:
Contractor:
McKee Utility Contractors, LLC
Consultant:
Lockwood Andrews & Newnam, Inc. (LAN)
Scope:
Construction Contract, Engineering Services During Construction, and Internal Inspection Services
Project:
No. 501-624-23, Stover Creek Force Main Segment B
Amount:
Construction Contract: $12,939,441
Engineering Services During Construction: $1,131,457
...
Click here for full text