title
Muddy Creek Wastewater Treatment Plant Expansion to 12.5 MGD and Operations Building Improvements; Project Nos. 310-0592-21 and 310-0535-19;
Tabulation of Bids and Award of Contract, Engineering Services Agreement, and Internal Inspection Services
end
SUBJECT
recommendation
Authorize award of a construction contract, engineering services agreement, and internal inspection services for the Wastewater Treatment Plant (WWTP) Expansion to 12.5 million gallons per day (MGD) and Operations Building Improvements projects.
end
PURPOSE
Address constraints in the existing facilities to improve the reliability of the existing WWTP and expand the WWTP capacity to meet the growth projections consistent with the 2021 Master Plan and 2022 Preliminary Engineering Report, which will reduce the risk of permit exceedances from peak wet weather events and expand the treatment capacity to meet the needs of the customers in the Cities of Wylie and Murphy.
RECOMMENDATION
The Executive Director and NTMWD staff recommend the Board of Directors authorize the award of a contract as follows:
Contractor:
Eagle Contracting, LLC
Consultant:
Garver, LLC
Scope:
Construction Contract, Engineering Services during Construction, and Internal Inspection Services
Project:
No. 310-0592-21 and 310-0535-21, Muddy Creek Wastewater Treatment Plant (WWTP) Expansion to 12.5 MGD and Operations Building Improvements
Amount:
$72,918,084 for construction contract
$2,883,566 for engineering services agreement
$2,164,980 for internal inspection services
Strategic Objective:
1.4 Reliable and Resilient Systems
Committee:
This will be an item on the April 24, 2024, Wastewater Committee meeting agenda
DRIVER(S) FOR THIS PROJECT
? Regulatory Compliance (pre-emptive)
? Asset Condition
? Capacity
? Redundancy/Resiliency
? Relocation or External Requests
? Operational Efficiency
? Safety
? Administrative
? Policy
? Other _____________
BACKGROUND
PROJECT PURPOSE
* Addre...
Click here for full text