Upper East Fork Interceptor System
title
Stover Creek Force Main;
Project No. 501-0624-23
Engineering Services Agreement - Right-of-Way Support Services
end
SUBJECT
recommendation
Authorize funding for professional services for the Stover Creek Force Main project.
end
PURPOSE
This action will provide for outsourced right-of-way support services to facilitate the planned right-of-way acquisition program for the Stover Creek Force Main project.
RECOMMENDATION
The Executive Director and NTMWD staff recommend the Board of Directors authorize the Executive Director to execute an engineering services agreement (ESA) as follows:
Consultant:
Lockwood, Andrews, & Newnam, Inc.
Scope:
Engineering Service Agreement; Right-of-Way support services
Project:
Project No. 501-0624-23, Stover Creek Force Main
Amount:
$2,331,606
Strategic Objective:
1.2 Successfully Deliver Capital Program
Committee:
This will be an item on the April 24, 2024, Wastewater Committee meeting agenda
DRIVER(S) FOR THIS PROJECT
? Regulatory Compliance
? Asset Condition
? Capacity
? Redundancy/Resiliency
? Relocation or External Requests
? Operational Efficiency
? Safety
? Administrative
? Policy
? Other _____________
BACKGROUND
PROJECT PURPOSE
* Increase wastewater conveyance capacity of the UEFIS by constructing a new lift station and force main to serve projected growth in McKinney and Prosper north of US 380.
* Return capacity to the McKinney-owned sewers and reduce risk of surcharge and sanitary sewer overflows.
* The planning level estimated construction cost for this project is $78,800,000.
PROJECT COMPONENTS
* Right-of-way support services for the acquisition of approximately 84 parcels consisting of permanent, temporary construction, and access easements for the thirteen-mile pipeline corridor.
* Condemnation support services will be performed by NTMWD.
BASIC SERVICES
* Outsourced land agent services
* Land agent administration services
...