Title: Stover Creek Force Main; Project No. 501-0624-23 Engineering Services Agreement - Right-of-Way Support Services
Sponsors: Wastewater Committee - Committee Action
Indexes: .UEFIS - Upper East Fork Interceptor System, Engineering Services Agreement
Code sections: 501-0624-23 - Stover Ck Force Main
Attachments: 1. Map
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
Upper East Fork Interceptor System

title
Stover Creek Force Main;
Project No. 501-0624-23
Engineering Services Agreement - Right-of-Way Support Services

end
SUBJECT

recommendation
Authorize funding for professional services for the Stover Creek Force Main project.
end

PURPOSE

This action will provide for outsourced right-of-way support services to facilitate the planned right-of-way acquisition program for the Stover Creek Force Main project.

RECOMMENDATION

The Executive Director and NTMWD staff recommend the Board of Directors authorize the Executive Director to execute an engineering services agreement (ESA) as follows:

Consultant:
Lockwood, Andrews, & Newnam, Inc.


Scope:

Engineering Service Agreement; Right-of-Way support services


Project:
Project No. 501-0624-23, Stover Creek Force Main


Amount:
$2,331,606


Strategic Objective:
1.2 Successfully Deliver Capital Program


Committee:
This will be an item on the April 24, 2024, Wastewater Committee meeting agenda








DRIVER(S) FOR THIS PROJECT

? Regulatory Compliance
? Asset Condition
? Capacity
? Redundancy/Resiliency
? Relocation or External Requests
? Operational Efficiency
? Safety
? Administrative
? Policy
? Other _____________

BACKGROUND

PROJECT PURPOSE
* Increase wastewater conveyance capacity of the UEFIS by constructing a new lift station and force main to serve projected growth in McKinney and Prosper north of US 380.
* Return capacity to the McKinney-owned sewers and reduce risk of surcharge and sanitary sewer overflows.
* The planning level estimated construction cost for this project is $78,800,000.

PROJECT COMPONENTS
* Right-of-way support services for the acquisition of approximately 84 parcels consisting of permanent, temporary construction, and access easements for the thirteen-mile pipeline corridor.
* Condemnation support services will be performed by NTMWD.

BASIC SERVICES
* Outsourced land agent services
* Land agent administration services
...