Title: Princeton Lift Station Expansion; Project No. 501-0617-22 Engineering Services Agreement
Sponsors: Wastewater Committee - Champion Update
Indexes: .UEFIS - Upper East Fork Interceptor System, Engineering Services Agreement
Code sections: 501-0617-22 - Princeton Lift Station Improvements
Attachments: 1. Map
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
Upper East Fork Interceptor System

title
Princeton Lift Station Expansion; Project No. 501-0617-22
Engineering Services Agreement
end

SUBJECT

recommendation
Authorize funding for engineering services for final design of the Princeton Lift Station Expansion project.
end

PURPOSE

The purpose of this project is to increase wastewater conveyance capacity serving growth in Princeton and to replace the lift station's roof due to condition.

RECOMMENDATION

The Executive Director and NTMWD staff recommend the Board of Directors authorize the Executive Director to execute an engineering services agreement (ESA) as follows:

Consultant:
AECOM Technical Services, Inc. (AECOM)


Scope:
Final Engineering Design


Project:
No. 501-0617-22, Princeton Lift Station Expansion


Amount:
$292,000


Strategic Objective:
1.2: Successfully Deliver Capital Program
1.4: Reliable and Resilient Systems


Committee:
This will be an item at the April 24, 2024, Wastewater Committee meeting agenda






DRIVER(S) FOR THIS PROJECT

? Regulatory Compliance
? Asset Condition
? Capacity
? Redundancy/Resiliency
? Relocation or External Requests
? Operational Efficiency
? Safety
? Administrative
? Policy
? Other _____________

BACKGROUND

PROJECT PURPOSE
* Increase the capacity of the Princeton Lift Station No. 2 from 12 million gallons per day (MGD) to approximately 14.7 MGD by increasing the size of the existing pump impellers as recommended in the Princeton Conceptual Design Report, by AECOM dated February 2024.
* Replace the existing lift station roof as recommended by the Princeton Lift Station Condition Assessment Report, by HDR, Inc., dated August 2023.
* The planning level estimated construction cost is $2,314,000.

PROJECT COMPONENTS
* Replace and upsize pump impellers
* Replace badly deteriorated roof

BASIC SERVICES
* Project management
* Final design engineering services
* Bid phase services

SPECIAL SERVICES
* None

ENGINEERING SERVICES FEE