File #: 24-6016    Version: 1
Type: Administrative Memorandum Status: Agenda Ready
File created: 4/10/2024 In control: Board of Directors
On agenda: 4/25/2024 Final action:
Title: Beck Branch Parallel Interceptor Phase II and Plano Spring Creek Force Main Parallel; Project No. 501-0439-16; Tabulation of Bids and Award of Contract and Inspection Services
Sponsors: Wastewater Committee - Committee Action
Indexes: .UEFIS - Upper East Fork Interceptor System, Tabulation of Bids - Award of Contract and Inspection Services
Code sections: 501-0439-16 - Beck Branch Interceptor Improvements
Attachments: 1. Map
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
Upper East Fork Interceptor System

title
Beck Branch Parallel Interceptor Phase II and Plano Spring Creek Force Main Parallel; Project No. 501-0439-16; Tabulation of Bids and Award of Contract and Inspection Services
end

SUBJECT

recommendation
Award a construction contract and authorize internal inspection services for the Beck Branch Parallel Interceptor Phase II and Plano Spring Creek Force Main Parallel portion of the Beck Branch Parallel Interceptor Improvements project.
end

PURPOSE

This action will award a contract for the construction of the incomplete portion of this project following the premature termination and demobilization of the original contractor, ARK Contracting Services, LLC, (ACS).

RECOMMENDATION

The Executive Director, NTMWD staff and Lockwood, Andrews, & Newnam, Inc. (LAN) recommend the Board of Directors authorize the award of a contract as follows:

Consultant:
Wilson Contractor Services, LLC


Scope:
Construction


Project:

No. 501-0439-16, Beck Branch Parallel Interceptor Phase II and Plano Spring Creek Force Main Parallel


Amount:

Construction Contract: $16,757,742.30
Inspection Services (internal): $333,250


Strategic Objective:
1.2 Successfully Deliver Capital Program
1.4 Reliable and Resilient System


Committee:
This will be an item on the April 24, 2024, Wastewater Committee meeting agenda


DRIVER(S) FOR THIS PROJECT

? Regulatory Compliance
? Asset Condition
? Capacity
? Redundancy/Resiliency
? Relocation or External Requests
? Operational Efficiency
? Safety
? Administrative
? Policy
? Other _____________


BACKGROUND

* On May 28, 2020, NTMWD executed a construction contract for the Beck Branch Parallel Interceptor Improvements, which consists of the Phase II portion of the Beck Branch Parallel Interceptor and the Plano Spring Creek Force Main Parallel, with ACS (Administrative Memorandum No. 5557).
* On July 21, 2023, ACS unilaterally terminated the contract before the construction contract was completed...